Shillong, Nov 26: The Supreme Court has upheld the order of the High Court in blacklisting a private road construction company for corrupt practices.
The BSC-C&C JV and BSCPL Infrastructure Ltd was blacklisted for five years for corrupt practices in the national highway project connecting Shillong-Nongstoin-Rongjeng-Tura completed in 2017 at the revised cost of over 2,400 crore.

Brief account below
- On 25.11.2026, the Supreme Court dismissed the Special Leave Petitions filed by M/s BSC-C&C JV (SLP (C) No. 15655 of 2026) and by its lead partner, M/s BSCPL Infrastructure Ltd. (SLP (C) No. 15820 of 2026), against the Public Works Department (Roads), Government of Meghalaya. A Bench of Justice M.M. Sundresh and Justice Prasanna B. Varale heard Senior Counsel Mukul Rohatgi for the petitioners and Amit Kumar, Senior Advocate, Advocate General, Meghalaya for the State. The Court found no reason to disturb the judgment of the High Court of Meghalaya. It held:
“We find no grounds to interfere with the impugned order(s) passed by the High Court. Accordingly, the Special Leave Petitions stand dismissed.”
With this order, the State’s order dated 03.12.2024, which debars the JV and both its partners for five years for indulging in acts of corruption from future tenders and contracts of PWD Meghalaya, stands upheld at every level of the judiciary.
Background
- In 2009, the Ministry of Road Transport and Highways floated a tender for two-laning of the Shillong–Nongstoin section of NH-44E and the Nongstoin–Rongjeng–Tura road under the Special Accelerated Road Development Programme for the North-East. The contract was executed with BSC-C&C JV on 21.02.2011 for Rs. 1,303.83 crore. The work was completed on 15.12.2017. Through four revised cost estimates, the cost rose to Rs. 2,406.46 crore.
- The JV then invoked arbitration and claimed about Rs. 487 crore more from the State. In support of its claim for delay costs, the JV filed its own ledgers. Its “Business Promotion” account recorded liquor, laptops, mobile phones, cameras, watches and other costly gifts for government officials, and hospitality for members of the Dispute Review Board.
- On this material, the Chief Engineer (NH), PWD (Roads) lodged a criminal complaint on 03.09.2024, and FIR No. 286(9) of 2024 was registered at Sadar Police Station, East Khasi Hills. The State issued a show cause notice on 16.09.2024 setting out the ledger entries. By a reasoned order dated 03.12.2024, the State debarred the JV and its partners for five years for indulging in corruption.
- The Single Judge of High Court of Meghalaya dismissed the writ petitions on 17.12.2025. A Division Bench of the Chief Justice Revati Mohite Dere and Justice W. Diengdoh dismissed the writ appeals on 19.02.2026. The Supreme Court also has now declined to interfere.
Issues involved
- The contractors argued that the State had no power to blacklist after the work was completed and the defect liability period had expired; that the order went beyond the show cause notice and no personal hearing was given; that the entries were ordinary festival and welfare expenses of about Rs. 9 lakh; that no official or favour in return was shown; and that five years was disproportionate.
- The core question was whether the State may debar a contractor for corrupt practices committed in the execution of a public works contract, after the contract has ended, on the basis of the contractor’s own records.
Significance of the decision
- The Division Bench held that the contract (Clause 37 of the Instructions to Bidders and Clause 59.2(h) of the General Conditions of Contract) permits action for corrupt practices in executing a contract, even after it is concluded. It also held that the State has an inherent right to choose with whom it does business and to debar entities that indulge in corrupt practices. It found that the show cause notice and the order rested on the contractor’s own ledgers, admitted in cross-examination; that the explanation offered was an afterthought; that natural justice was complied with; and that there was neither delay nor mala fides. The Court stressed that public interest and public money come first:
“The State is under an obligation to put public interest over everything else. After all, the monies utilised is public money, which cannot be lost sight of.”
- The decision and messag from Govt Completion of a project is no shield for corruption in its execution. A contractor who offers gifts and hospitality to public officials cannot recover those sums from the exchequer and then call them business expenses. With concurrent findings of the Single Judge, the Division Bench and now the Hon’ble Supreme Court, the State’s action stands fully vindicated.
The stand of the State and role of the Advocate General
- The State acted on its own initiative to protect public funds and the integrity of its public works. It identified the entries in the contractor’s own records, set the criminal law in motion, followed due process and defended its decision through three tiers of courts.
- Amit Kumar, Senior Advocate, Advocate General, Meghalaya, led the State’s case at every stage. He represented the State before the Arbitral Tribunal, where the ledgers came on record. He argued the writ petitions before the Single Judge over several hearings in 2025, and the writ appeals before the Division Bench in February 2026. He argued the Special Leave Petitions before the Supreme Court on 25.11.2026. He showed that the charge of corruption rested on the contractor’s own records, which it never denied, and that the findings of the courts below were concurrent. He was assisted in the Supreme Court by Aditya Shanker Pandey, Advocate-on-Record, and Himanshu Sehrawat, Advocate, and in the High Court by A.H. Kharwanlang, Additional Senior . Government Advocate A.S. Pandey, Government Advocates S. Laloo and I. Syiemlieh.
The criminal case arising from FIR No. 286(9) of 2024 remains under investigation and will take its own course in accordance with law.